Here is a proposed release schedule for 0.14.0. Like for previous major releases I’ve added 6 months to the previous release schedule (#7679), even though 0.13.0 was moved forward a month compared to the original planning. This means the planned release of 0.14.0 will be a month later compared to the planned release date of 0.12.0 last year.
0Proposed release schedule for 0.14.0:
1
22017-01-02
3-----------
4- Open Transifex translations for 0.14
5- Soft translation string freeze (no large or unnecessary string changes until release)
6- Finalize and close translations for 0.12
7
82017-01-16
9-----------
10- Feature freeze (bug fixes only until release)
11- Translation string freeze (no more source language changes until release)
12
132017-02-06
14-----------
15- Split off `0.14` branch from `master`
16- Start RC cycle, tag and release `0.14.0rc1`
17- Start merging for 0.15 on master branch
18
192017-03-01
20-----------
21- Release 0.14.0 final (aim)